> We completed Milestone 1 today (yeah! and a big Thank You!!) and we have
> started Milestone 2. Our goal is to have a very stable Milestone 2. With
> this in mind, Carla and I put together the exit criteria for Milestone
> 2. The expectation is high -- especially the bug fixing requirements
> are very steep compared to previous milestones. Milestone 2 dates are:
> freeze (9/12) and completion (9/26). (The 2 weeks between freeze and
> completion should be stabilization period to fix bugs)
>
> http://www.glassfishwiki.org/gfwiki/Wiki.jsp?page=Milestone2ExitCriteria
>
> Please review the criteria and let me know if you have questions/concerns.
>
> thanks
> -Sridatta
>
> ---------------------------------------------------------------------