dev@glassfish.java.net

Re: ACTION: Pl review GlassFish v2 Milestone 2 Exit Criteria

From: Marina Vatkina <Marina.Vatkina_at_Sun.COM>
Date: Thu, 17 Aug 2006 14:38:10 -0700

Sridatta,

These rules rely on bugs being evaluated. There is no such option in the
issue tracker. Can we come up with a different strategy?

thanks,
-marina

Sridatta Viswanath wrote:
> We completed Milestone 1 today (yeah! and a big Thank You!!) and we have
> started Milestone 2. Our goal is to have a very stable Milestone 2. With
> this in mind, Carla and I put together the exit criteria for Milestone
> 2. The expectation is high -- especially the bug fixing requirements
> are very steep compared to previous milestones. Milestone 2 dates are:
> freeze (9/12) and completion (9/26). (The 2 weeks between freeze and
> completion should be stabilization period to fix bugs)
>
> http://www.glassfishwiki.org/gfwiki/Wiki.jsp?page=Milestone2ExitCriteria
>
> Please review the criteria and let me know if you have questions/concerns.
>
> thanks
> -Sridatta
>
> ---------------------------------------------------------------------
> To unsubscribe, e-mail: dev-unsubscribe_at_glassfish.dev.java.net
> For additional commands, e-mail: dev-help_at_glassfish.dev.java.net
>