Marina Vatkina wrote:
> Sridatta,
>
> These rules rely on bugs being evaluated. There is no such option in the
> issue tracker. Can we come up with a different strategy?

I'd think evaluated = STARTED state according to Issue Tracker issue
life cycle doc [1].

[1] https://glassfish.dev.java.net/scdocs/issue_lifecycle.html

hth,
Amy

>
> thanks,
> -marina
>
> Sridatta Viswanath wrote:
>
>> We completed Milestone 1 today (yeah! and a big Thank You!!) and we
>> have started Milestone 2. Our goal is to have a very stable Milestone
>> 2. With this in mind, Carla and I put together the exit criteria for
>> Milestone 2. The expectation is high -- especially the bug fixing
>> requirements are very steep compared to previous milestones.
>> Milestone 2 dates are: freeze (9/12) and completion (9/26). (The 2
>> weeks between freeze and completion should be stabilization period to
>> fix bugs)
>>
>> http://www.glassfishwiki.org/gfwiki/Wiki.jsp?page=Milestone2ExitCriteria
>>
>> Please review the criteria and let me know if you have
>> questions/concerns.
>>
>> thanks
>> -Sridatta
>>
>> ---------------------------------------------------------------------
>> To unsubscribe, e-mail: dev-unsubscribe_at_glassfish.dev.java.net
>> For additional commands, e-mail: dev-help_at_glassfish.dev.java.net
>>
>
> ---------------------------------------------------------------------
> To unsubscribe, e-mail: dev-unsubscribe_at_glassfish.dev.java.net