attached mail follows:
Hello All,
We are approaching our deadline (*10/4/2006*) for deciding the Milestone
3 (MS3) freeze date and exit criteria.
Please provide us input/feedback on our proposal by updating the wiki
page
<
http://www.glassfishwiki.org/gfwiki/Wiki.jsp?page=GFv2MS3CriteriaInputFromEngineers>
This will help us in having a realistic feature freeze date and bug
criteria for MS3.
Thanks in advance,
-Dhiru
=======================================================================================
GlassFish v2/Appserver 9.1 Developers,
***READ and TAKE ACTION***
Thanks again for significant progress made in Milestone2. We are
starting to work on Milestone 3 (MS3). The beta release (of both GF v2
and SDK) is scheduled for Jan 15, 2007. The beta date is a slight change
from the original proposal of Dec 11 and this change helps align with
SDK release. The milestone page
<
http://www.glassfishwiki.org/gfwiki/Wiki.jsp?page=Milestones> has been
updated to reflect this change. FCS is still targeted for Apr 07. Here
is a summary of remaining milestones and proposed criteria:
* MS3 Freeze (Feature complete) is Oct 31, 2006
o Criteria: All Features completed
o All JSR MRs filed and changes implemented
* MS3 completion is Dec 11, 2006
o No P1s.
o Max 2 P2s per module (combined bugster dashboard
<
http://monaco.sfbay/summary.jsf?product=sunone_application_server&hook4Opt=2&area=Defect&CRrelease=null%2C9*&hook4=as91-na%2Cas91-fixed&title=Open+Bugs+with+Target+Release+9*%2C+null&hook2=as9-na&hook2Opt=2>
and issue tracker dashboard
<
https://glassfish.dev.java.net/issues/reports.cgi?state=Open+issues&issue_type=DEFECT&containing=&type=case-insensitive+substring&x=Subcomponent&y=Priority>)
o All P3/S1 bugster bugs
<
http://monaco.sfbay/list.jsf?product=sunone_application_server&hook4Opt=2&area=Defect&CRrelease=null%2C9*&hook4=as91-na%2Cas91-fixed&title=Open+Bugs+with+Target+Release+9*%2C+null&hook2=as9-na&severity=1&priority=3&hook2Opt=2>
need to be fixed
o Forward port all 8.2 bugs <
http://monaco.sfbay/url/8t0>
o P3s per module cannot exceed a max number. (Tell us what
this should be for your module. You will need to resolve all
P3s by FCS in any case. So, a higher cap means more bugs
towards the end and is more risky)
* Beta Release is Jan 15 2007
o Bug Criteria: No P1, No P2
* FCS is Apr 07
o Bug Criteria: No P1s, No P2s, No P3s (and no unevaluated S1s
in bugster)
To have a realistic feature freeze date and bug criteria, we would like
to seek input from all of you. So, please provide input on the following
by updating the wiki page
<
http://www.glassfishwiki.org/gfwiki/Wiki.jsp?page=GFv2MS3CriteriaInputFromEngineers>:
* Will you be able to complete your features by Oct 31? If not, when
will it be done? Please mention performance changes separately.
* Will you be able to meet proposed bug criteria
<
http://www.glassfishwiki.org/gfwiki/Wiki.jsp?page=Milestone3ExitCriteria>?
If not, what is a realistic goal for Dec 11?
* Provide a max number for P3s (bugster and issuetracker combined)
for your module (for module leads).
*Please update the wiki page
<
http://www.glassfishwiki.org/gfwiki/Wiki.jsp?page=GFv2MS3CriteriaInputFromEngineers>
with your input before 10/4.*
(Do not reply to this mail with your input)
thanks
-Sridatta, Dhiru, Carla.