Hi Ken,
Thanks for updating the Wiki. We will be finalizing the milestone 3 (M3)
dates and exit criteria soon, based on the input given by everyone.
-Dhiru
Ken Cavanaugh wrote:
> Dhiru,
>
> I've update both tables. At present, I have two CORBA features:
> CORBA/Grizzly integration and CORBA
> optimization. I think we will need until (at least) 11/20 to finish
> the CORBA integration. The currently
> planned optimization work should be done by 10/31, but we'll see as we
> go what else comes up.
>
> Call me if you need to discuss this further.
>
> Thanks,
>
> Ken.
>