Enter unit information for resource assignments

  1. Choose Project, Activities.
  2. Select the activity whose unit values you want to record.
  3. Display Activity Details, then click the Resources tab.
  4. To enter the budgeted or planned units for the activity, type the value in the budgeted or planned Units column.

    To enter the actual units for the activity, type the value in the Actual Units column. You can only enter actual units for activities that are in progress or completed.

    To enter the remaining units for the activity, type the value in the Remaining Units column. You can only enter remaining units for activities that are in progress.

    Note

    A time period does not display if the Show Unit Label checkbox is not marked in the User Preferences, Time Units tab.

Tip

Related Topics

Synchronizing activity duration, units, and resource units/time