Enter a physical percent complete for activities

A percent complete that is entered manually by the user instead of being calculated by the module is known as a "physical" percent complete.

The default method is to calculate percent complete according to activity duration.

  1. Choose Project, Activities.
  2. Select the activity whose physical percent complete you want to enter.
  3. Display Activity Details, then click the General tab.
  4. Select Physical as the percent complete type.
  5. Click the Status tab.
  6. In the Physical % field, type a physical percent complete.

    Note

    You may enter a percent complete value for in progress activities only. If the activity has not started yet or has already finished, you will not be able to specify a percent complete value.