What to do: |
|
| In order to work through this example you must have completed the example Set up a CM Project. | |
| A baseline is exclusively used to introduce a new product and record the original configuration as is planned. | |
| Select . The mask is opened. |
|
|
To change to insert mode click |
|
| Click The list is opened. |
|
| Search for the CM project Project-01 and select it from the list. | |
| Enter Baseline-01 in the field and Baseline for Ball Pen Deluxe in the field. | |
| Click |
|
![]() |
|
| To save the entry click |
|
| The following result will be displayed in the message window. | |
| Please note that when creating a baseline a default work set is automatically created as well. The work set is displayed in the tab of the mask as follows: | |
![]() |
|
| The baseline contains all approved/released items and documents representing the configuration for a set of products (models + units) at a specific point in time. |