What to do: |
|
| In order to work through this example, you must have created the object ART-1450 Green Ink. For our example it is not important if this object has been created in an ad-hoc or non-ad-hoc process. Furthermore, you must have created a new work request. In our example the new work request is EWR-1510. | |
| Please note that in this example the change operation is to create a new version of an existing object. | |
| Select .
The mask is opened. |
|
|
Search for the item ART-1450. |
|
| Change to the status 220 | Approved. | |
| Activate the corresponding work set EWR-1500. | |
|
In the mask click the
button in order to release the work set.
|
|
| In the
field enter a validity date for the work set and click
to confirm. The work set EWR-1500 is set to the state 270 | Complete. |
|
| To update the
mask click The item ART-1450 is automatically set to the state 230 | Released. |
|
| Change the status of the item ART-1450 to 240 | In Change. | |
| On the mask
of ART-1450 select from the context
menu. A new mask of ART-1450 is opened. |
|
| In the field select the work order EWR-1510. | |
| The work request / work order EWR-1510 is needed as a reference work order / work set for the final process of creating an item. The work order EWR-1500 cannot be used again since it was used up for the completion of the work set EWR-1500. | |
| To save the entry click |
|
|
A new version of the item ART-1450 has been created.
|
|
| The predecessor version of the item ART-1450 will become invalid when the work set EWR-1510 is completed and the new item version has become effective. The validity is indicated in the field of the item mask. | |
| Please note that a new object version can only be created if the referenced work set is in state 110 | In Work. | |
| Instead of creating a new work request EWR-1510, it is also possible to add an additional set to the work order EWR-1500 and reference this work set. |