What to do: |
|
| In order to work through this example you must have created a new work request EWR-2000 for the creation of a new BOM and must have created the items displayed below. | |
![]() |
|
| When creating the items displayed above it is sufficient to reference the work request / work order EWR-2000 for each of them. | |
| Search for the item ART-1000 EP Ballpen. | |
| Select the tab. | |
|
To change to insert mode click |
|
| In the field
click |
|
| In the
field click The list is opened. |
|
| Select the item ART-1100 Lower Part. | |
| To save the entry click |
|
| Repeat the steps 3 to 7 to add the other items to the BOM. | |
![]() |
|
| A new BOM with multiple item structure relations has been created. | |
| Please note that the items within the BoM are preliminary items. As long as the items are "preliminary" and in the state 110 | In Work, they can be modified without the use of a change operation! |