Resource Assignments
P6 EPPM Field | IPMDAR Field |
|---|---|
Resource ID | ResourceID |
Activity ID | TaskID |
Budget At Completion (Dollars) | Budget_AtCompletion_Dollars |
Budget At Completion (Hours) | Budget_AtCompletion_Hours |
Estimate To Complete (Dollars) | Estimate_ToComplete_Dollars |
Estimate To Complete (Hours) | Estimate_ToComplete_Hours |
Actual Cost | Actual_ToDate_Dollars |
Actual Units | Actual_ToDate_Hours |
Assignment % Complete | PhysicalPercentComplete |