Task Schedule Data
P6 EPPM Field | IPMDAR Field |
|---|---|
Activity ID/Code | Task ID |
Calendar DB ID | Calendar ID |
Remaining Duration | Current Duration |
Start | Current Start Date |
Finish | Current Finish Date |
Early Start (for WBS Summary. the earliest Early Start Date of all activities in that WBS node) | Early Start Date |
Early Finish (for WBS Summary. the earliest Early Finish Date of all activities in that WBS node) | Early Finish Date |
Late Start (for WBS Summary. the earliest Late Start Date of all activities in that WBS node) | Late Start Date |
Late Finish (for WBS Summary. the earliest Late Finish Date of all activities in that WBS node) | Late Finish Date |
Free Float | Free Float Duration |
Total Float | Total Float Duration |
Critical | On Critical Path |
On Driving Path | On Driving Path |
BL Project Duration | Baseline Duration |
BL Project Start | Baseline Start Date |
BL Project Finish | Baseline Finish Date |
Variance BL Project – Start Date | Start Variance Duration |
Variance BL Project – Finish Date | Finish Variance Duration |
Activity % Complete | Calculated % Complete |
Physical % Complete | Physical % Complete |
Remaining Duration | Remaining Duration |
Actual Start | Actual Start Date |
Actual Finish | Actual Finish Date |
Last Published Tuesday, December 9, 2025