Task Schedule Data

P6 EPPM Field

IPMDAR Field

Activity ID/Code

Task ID

Calendar DB ID

Calendar ID

Remaining Duration

Current Duration

Start

Current Start Date

Finish

Current Finish Date

Early Start

(for WBS Summary. the earliest Early Start Date of all activities in that WBS node)

Early Start Date

Early Finish

(for WBS Summary. the earliest Early Finish Date of all activities in that WBS node)

Early Finish Date

Late Start

(for WBS Summary. the earliest Late Start Date of all activities in that WBS node)

Late Start Date

Late Finish

(for WBS Summary. the earliest Late Finish Date of all activities in that WBS node)

Late Finish Date

Free Float

Free Float Duration

Total Float

Total Float Duration

Critical

On Critical Path

On Driving Path

On Driving Path

BL Project Duration

Baseline Duration

BL Project Start

Baseline Start Date

BL Project Finish

Baseline Finish Date

Variance BL Project – Start Date

Start Variance Duration

Variance BL Project – Finish Date

Finish Variance Duration

Activity % Complete

Calculated % Complete

Physical % Complete

Physical % Complete

Remaining Duration

Remaining Duration

Actual Start

Actual Start Date

Actual Finish

Actual Finish Date