Tasks
P6 EPPM Field | IPMDAR Field |
|---|---|
Activity ID/Code | ID |
Activity Name | Name |
Activity Type | Task Type ID |
Activity Code or UDF value | Task Subtype ID |
Activity Code or UDF value | Task Planning Level ID |
WBS | WBS Element ID |
Responsible Manager | OBS Element ID |
Activity Code or UDF value. Includes WBS and Activity UDFs, and Activity Codes. | Control Account ID |
Activity Code or UDF value. Includes WBS and Activity UDFs, and Activity Codes. | Work Package ID |
Activity Code or UDF value | IMP Element ID |
Activity Code or UDF value | SOW Reference |
Activity Code or UDF value | Subcontractor Reference |
Technique for computing performance percent complete | Earned Value Technique ID |
Activity Code or UDF value | Other Earned Value Technique |
Activity Code or UDF value | Source Subproject Reference |
Activity Code or UDF value | Source Task Reference |
Activity Code or UDF value | Comments |