DS05 Schedule Logic
Note Relationships to activities outside the set of projects being exported are represented by relationships to placeholder tasks with a subtype of SVT.
CPP Field Name | CPP Field Description | P6 Source |
|---|---|---|
PARSID | Project Assessment and Reporting System identifier for the project submitted. | Entered in the template. |
CPP_status_date | Contractor "as-of" date. | Entered in the template. |
schedule_type | Describes whether the schedule is a baseline (BL) or forecast (FC). | Project type |
task_ID | Task identifier of the successor. | Activity ID (Successor) |
predecessor_task_ID | Task identifier of the predecessor. | Activity ID (Predecessor) |
type | Determines whether the relationship between task and predecessor is finish to start (FS), start to start (SS), start to finish (SF), or finish to finish (FF) | Relationship Type |
lag_days | Task relationship lag, based on predecessor's calendar. A positive figure represents lag, a negative figure represents lead. | Lag |
subproject_ID | Unique subproject identifier. | Project Short Name of the predecessor activity's project. |