Interface ActivitySpreadPeriod
- All Superinterfaces:
SpreadPeriod
This interface defines all access methods for each resource assignment spread period. The spread
period is calculated according to the bucket type.
-
Method Summary
Modifier and TypeMethodDescriptionGets the actual cost for this spread period.Gets the actual expense cost for this spread period.Gets the actual labor cost for this spread period.Gets the actual labor units for this spread period.Gets the actual material cost for this spread period.Gets the actual nonlabor cost for this spread period.Gets the actual nonlabor units for this spread period.Gets the actual total cost for this spread period.Gets the at completion expense cost for this spread period.Gets the at completion labor cost for this spread period.Gets the at completion labor units for this spread period.Gets the at completion material cost for this spread period.Gets the at completion nonlabor cost for this spread period.Gets the at completion nonlabor units for this spread period.Gets the at completion total cost for this spread period.Gets the primary baseline actual expense cost for this spread period.Gets the primary baseline actual labor cost for this spread period.Gets the primary baseline actual labor units for this spread period.Gets the primary baseline actual material cost for this spread period.Gets the primary baseline actual nonlabor cost for this spread period.Gets the primary baseline actual nonlabor units for this spread period.Gets the primary baseline actual total cost for this spread period.Gets the primary baseline planned expense cost for this spread period.Gets the primary baseline planned labor cost for this spread period.Gets the primary baseline planned labor units for this spread period.Gets the primary baseline planned material cost for this spread period.Gets the primary baseline planned nonlabor cost for this spread period.Gets the primary baseline planned nonlabor units for this spread period.Gets the primary baseline planned total cost for this spread period.Gets the project baseline actual expense cost for this spread period.Gets the project baseline actual labor cost for this spread period.Gets the project baseline actual labor units for this spread period.Gets the project baseline actual material cost for this spread period.Gets the project baseline actual nonlabor cost for this spread period.Gets the project baseline actual nonlabor units for this spread period.Gets the project baseline actual total cost for this spread period.Gets the project baseline planned expense cost for this spread period.Gets the project baseline planned labor cost for this spread period.Gets the project baseline planned labor units for this spread period.Gets the project baseline planned material cost for this spread period.Gets the project baseline planned nonlabor cost for this spread period.Gets the project baseline planned nonlabor units for this spread period.Gets the project baseline planned total cost for this spread period.Gets the cumulative actual cost for this spread period, which is cumulated from the activity start to the end of this period.Gets the cumulative actual expense cost for this spread period, which is cumulated from the activity start to the end of this period.Gets the cumulative actual labor cost for this spread period, which is cumulated from the activity start to the end of this period.Gets the cumulative actual labor units for this spread period, which is cumulated from the activity start to the end of this period.Gets the cumulative actual material cost for this spread period, which is cumulated from the activity start to the end of this period.Gets the cumulative actual nonlabor cost for this spread period, which is cumulated from the activity start to the end of this period.Gets the cumulative actual nonlabor units for this spread period, which is cumulated from the activity start to the end of this period.Gets the cumulative actual total cost for this spread period, which is cumulated from the activity start to the end of this period.Gets the cumulative at completion expense cost for this spread period, which is cumulated from the activity start to the end of this period.Gets the cumulative at completion labor cost for this spread period, which is cumulated from the activity start to the end of this period.Gets the cumulative at completion labor units for this spread period, which is cumulated from the activity start to the end of this period.Gets the cumulative at completion material cost for this spread period, which is cumulated from the activity start to the end of this period.Gets the cumulative at completion nonlabor cost for this spread period, which is cumulated from the activity start to the end of this period.Gets the cumulative at completion nonlabor units for this spread period, which is cumulated from the activity start to the end of this period.Gets the cumulative at completion total cost for this spread period, which is cumulated from the activity start to the end of this period.Gets the cumulative primary baseline actual expense cost for this spread period, which is cumulated from the activity start to the end of this period.Gets the cumulative primary baseline actual labor cost for this spread period, which is cumulated from the activity start to the end of this period.Gets the cumulative primary baseline actual labor units for this spread period, which is cumulated from the activity start to the end of this period.Gets the cumulative primary baseline actual material cost for this spread period, which is cumulated from the activity start to the end of this period.Gets the cumulative primary baseline actual nonlabor cost for this spread period, which is cumulated from the activity start to the end of this period.Gets the cumulative primary baseline actual nonlabor units for this spread period, which is cumulated from the activity start to the end of this period.Gets the cumulative primary baseline actual total cost for this spread period, which is cumulated from the activity start to the end of this period.Gets the cumulative primary baseline planned expense cost for this spread period, which is cumulated from the activity start to the end of this period.Gets the cumulative primary baseline planned labor cost for this spread period, which is cumulated from the activity start to the end of this period.Gets the cumulative primary baseline planned labor units for this spread period, which is cumulated from the activity start to the end of this period.Gets the cumulative primary baseline planned material cost for this spread period, which is cumulated from the activity start to the end of this period.Gets the cumulative primary baseline planned nonlabor cost for this spread period, which is cumulated from the activity start to the end of this period.Gets the cumulative primary baseline planned nonlabor units for this spread period, which is cumulated from the activity start to the end of this period.Gets the cumulative primary baseline planned total cost for this spread period, which is cumulated from the activity start to the end of this period.Gets the cumulative project baseline actual expense cost for this spread period, which is cumulated from the activity start to the end of this period.Gets the cumulative project baseline actual labor cost for this spread period, which is cumulated from the activity start to the end of this period.Gets the cumulative project baseline actual labor units for this spread period, which is cumulated from the activity start to the end of this period.Gets the cumulative project baseline actual material cost for this spread period, which is cumulated from the activity start to the end of this period.Gets the cumulative project baseline actual nonlabor cost for this spread period, which is cumulated from the activity start to the end of this period.Gets the cumulative project baseline actual nonlabor units for this spread period, which is cumulated from the activity start to the end of this period.Gets the cumulative project baseline actual total cost for this spread period, which is cumulated from the activity start to the end of this period.Gets the cumulative project baseline planned expense cost for this spread period, which is cumulated from the activity start to the end of this period.Gets the cumulative project baseline planned labor cost for this spread period, which is cumulated from the activity start to the end of this period.Gets the cumulative project baseline planned labor units for this spread period, which is cumulated from the activity start to the end of this period.Gets the cumulative project baseline planned material cost for this spread period, which is cumulated from the activity start to the end of this period.Gets the cumulative project baseline planned nonlabor cost for this spread period, which is cumulated from the activity start to the end of this period.Gets the cumulative project baseline planned nonlabor units for this spread period, which is cumulated from the activity start to the end of this period.Gets the cumulative project baseline planned total cost for this spread period, which is cumulated from the activity start to the end of this period.Gets the cumulative earned value cost for this spread period, which is cumulated from the activity start to the end of this period.Gets the cumulative earned value labor units for this spread period, which is cumulated from the activity start to the end of this period.Gets the cumulative estimate at completion cost for this spread period, which is cumulated from the activity start to the end of this period.Gets the cumulative estimate at completion labor units for this spread period, which is cumulated from the activity start to the end of this period.Gets the cumulative estimate to completion for this spread period, which is cumulated from the activity start to the end of this period.Gets the cumulative estimate to completion labor units for this spread period, which is cumulated from the activity start to the end of this period.Gets the cumulative planned expense cost for this spread period, which is cumulated from the activity start to the end of this period.Gets the cumulative planned labor cost for this spread period, which is cumulated from the activity start to the end of this period.Gets the cumulative planned labor units for this spread period, which is cumulated from the activity start to the end of this period.Gets the cumulative planned material cost for this spread period, which is cumulated from the activity start to the end of this period.Gets the cumulative planned nonlabor cost for this spread period, which is cumulated from the activity start to the end of this period.Gets the cumulative planned nonlabor units for this spread period, which is cumulated from the activity start to the end of this period.Gets the cumulative planned total cost for this spread period, which is cumulated from the activity start to the end of this period.Gets the cumulative planned value cost for this spread period, which is cumulated from the activity start to the end of this period.Gets the cumulative planned value labor units for this spread period, which is cumulated from the activity start to the end of this period.Gets the cumulative remaining expense cost for this spread period, which is cumulated from the activity start to the end of this period.Gets the cumulative remaining labor cost for this spread period, which is cumulated from the activity start to the end of this period.Gets the cumulative remaining labor units for this spread period, which is cumulated from the activity start to the end of this period.Gets the cumulative remaining late expense cost for this spread period, which is cumulated from the activity start to the end of this period.Gets the cumulative remaining late labor cost for this spread period, which is cumulated from the activity start to the end of this period.Gets the cumulative remaining late labor units for this spread period, which is cumulated from the activity start to the end of this period.Gets the cumulative remaining late material cost for this spread period, which is cumulated from the activity start to the end of this period.Gets the cumulative remaining late nonlabor cost for this spread period, which is cumulated from the activity start to the end of this period.Gets the cumulative remaining late nonlabor units for this spread period, which is cumulated from the activity start to the end of this period.Gets the cumulative remaining late total cost for this spread period, which is cumulated from the activity start to the end of this period.Gets the cumulative remaining material cost for this spread period, which is cumulated from the activity start to the end of this period.Gets the cumulative remaining nonlabor cost for this spread period, which is cumulated from the activity start to the end of this period.Gets the cumulative remaining nonlabor units for this spread period, which is cumulated from the activity start to the end of this period.Gets the cumulative remaining total cost for this spread period, which is cumulated from the activity start to the end of this period.Gets the earned value cost for this spread period.Gets the earned value labor units for this spread period.Gets the estimate at completion cost for this spread period.Gets the estimate at completion labor units for this spread period.Gets the estimate to completion for this spread period.Gets the estimate to completion labor units for this spread period.Gets the planned expense cost for this spread period.Gets the planned labor cost for this spread period.Gets the planned labor units for this spread period.Gets the planned material cost for this spread period.Gets the planned nonlabor cost for this spread period.Gets the planned nonlabor units for this spread period.Gets the planned total cost for this spread period.Gets the planned value cost for this spread period.Gets the planned value labor units for this spread period.Gets the remaining expense cost for this spread period.Gets the remaining labor cost for this spread period.Gets the remaining labor units for this spread period.Gets the remaining late expense cost for this spread period.Gets the remaining late labor cost for this spread period.Gets the remaining late labor units for this spread period.Gets the remaining late material cost for this spread period.Gets the remaining late nonlabor cost for this spread period.Gets the remaining late nonlabor units for this spread period.Gets the remaining late total cost for this spread period.Gets the remaining material cost for this spread period.Gets the remaining nonlabor cost for this spread period.Gets the remaining nonlabor units for this spread period.Gets the remaining total cost for this spread period.Methods inherited from interface com.primavera.common.value.spread.SpreadPeriod
getCost, getCumulativeCost, getCumulativeUnits, getSpreadBucketType, getSpreadBucketTypeEnum, getSpreadPeriodEnd, getSpreadPeriodStart, getUnits, setCost, setUnits
-
Method Details
-
getBaseline1PlannedLaborCost
Gets the primary baseline planned labor cost for this spread period.- Returns:
- the primary baseline planned labor cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativeBaseline1PlannedLaborCost
Cost getCumulativeBaseline1PlannedLaborCost() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative primary baseline planned labor cost for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated primary baseline planned labor cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-
getBaselineActualTotalCost
Gets the project baseline actual total cost for this spread period.- Returns:
- the project baseline actual total cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativeBaselineActualTotalCost
Cost getCumulativeBaselineActualTotalCost() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative project baseline actual total cost for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated project baseline actual total cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-
getPlannedNonLaborCost
Gets the planned nonlabor cost for this spread period.- Returns:
- the planned nonlabor cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativePlannedNonLaborCost
Cost getCumulativePlannedNonLaborCost() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative planned nonlabor cost for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated planned nonlabor cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-
getEstimateToCompleteLaborUnits
Gets the estimate to completion labor units for this spread period.- Returns:
- the estimate to complete labor units in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativeEstimateToCompleteLaborUnits
Unit getCumulativeEstimateToCompleteLaborUnits() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative estimate to completion labor units for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated estimate to complete labor units in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-
getAtCompletionLaborUnits
Gets the at completion labor units for this spread period.- Returns:
- the at completion labor units in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativeAtCompletionLaborUnits
Unit getCumulativeAtCompletionLaborUnits() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative at completion labor units for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated at completion labor units in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-
getActualMaterialCost
Gets the actual material cost for this spread period.- Returns:
- the actual material cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativeActualMaterialCost
Cost getCumulativeActualMaterialCost() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative actual material cost for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated actual material cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-
getRemainingNonLaborCost
Gets the remaining nonlabor cost for this spread period.- Returns:
- the remaining nonlabor cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativeRemainingNonLaborCost
Cost getCumulativeRemainingNonLaborCost() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative remaining nonlabor cost for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated remaining nonlabor cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-
getRemainingLateNonLaborCost
Gets the remaining late nonlabor cost for this spread period.- Returns:
- the remaining late nonlabor cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativeRemainingLateNonLaborCost
Cost getCumulativeRemainingLateNonLaborCost() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative remaining late nonlabor cost for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated remaining late nonlabor cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-
getBaselinePlannedLaborCost
Gets the project baseline planned labor cost for this spread period.- Returns:
- the project baseline planned labor cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativeBaselinePlannedLaborCost
Cost getCumulativeBaselinePlannedLaborCost() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative project baseline planned labor cost for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated project baseline planned labor cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-
getBaseline1PlannedLaborUnits
Gets the primary baseline planned labor units for this spread period.- Returns:
- the primary baseline planned labor units in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativeBaseline1PlannedLaborUnits
Unit getCumulativeBaseline1PlannedLaborUnits() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative primary baseline planned labor units for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated primary baseline planned labor units in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-
getPlannedExpenseCost
Gets the planned expense cost for this spread period.- Returns:
- the planned expense cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativePlannedExpenseCost
Cost getCumulativePlannedExpenseCost() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative planned expense cost for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated planned expense cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-
getPlannedNonLaborUnits
Gets the planned nonlabor units for this spread period.- Returns:
- the planned nonlabor units in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativePlannedNonLaborUnits
Unit getCumulativePlannedNonLaborUnits() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative planned nonlabor units for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated planned nonlabor units in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-
getBaseline1PlannedNonLaborUnits
Gets the primary baseline planned nonlabor units for this spread period.- Returns:
- the primary baseline planned nonlabor units in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativeBaseline1PlannedNonLaborUnits
Unit getCumulativeBaseline1PlannedNonLaborUnits() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative primary baseline planned nonlabor units for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated primary baseline planned nonlabor units in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-
getPlannedTotalCost
Gets the planned total cost for this spread period.- Returns:
- the planned total cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativePlannedTotalCost
Cost getCumulativePlannedTotalCost() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative planned total cost for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated planned total cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-
getAtCompletionTotalCost
Gets the at completion total cost for this spread period.- Returns:
- the at completion total cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativeAtCompletionTotalCost
Cost getCumulativeAtCompletionTotalCost() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative at completion total cost for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated at completion total cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-
getActualTotalCost
Gets the actual total cost for this spread period.- Returns:
- the actual total cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativeActualTotalCost
Cost getCumulativeActualTotalCost() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative actual total cost for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated actual total cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-
getEstimateAtCompletionCost
Gets the estimate at completion cost for this spread period.- Returns:
- the estimate at completion cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativeEstimateAtCompletionCost
Cost getCumulativeEstimateAtCompletionCost() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative estimate at completion cost for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated estimate at completion cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-
getPlannedValueCost
Gets the planned value cost for this spread period.- Returns:
- the planned value cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativePlannedValueCost
Cost getCumulativePlannedValueCost() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative planned value cost for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated planned value cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-
getBaselineActualNonLaborUnits
Gets the project baseline actual nonlabor units for this spread period.- Returns:
- the project baseline actual nonlabor units in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativeBaselineActualNonLaborUnits
Unit getCumulativeBaselineActualNonLaborUnits() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative project baseline actual nonlabor units for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated project baseline actual nonlabor units in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-
getBaselineActualNonLaborCost
Gets the project baseline actual nonlabor cost for this spread period.- Returns:
- the project baseline actual nonlabor cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativeBaselineActualNonLaborCost
Cost getCumulativeBaselineActualNonLaborCost() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative project baseline actual nonlabor cost for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated project baseline actual nonlabor cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-
getRemainingTotalCost
Gets the remaining total cost for this spread period.- Returns:
- the remaining total cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativeRemainingTotalCost
Cost getCumulativeRemainingTotalCost() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative remaining total cost for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated remaining total cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-
getRemainingLateTotalCost
Gets the remaining late total cost for this spread period.- Returns:
- the remaining late total cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativeRemainingLateTotalCost
Cost getCumulativeRemainingLateTotalCost() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative remaining late total cost for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated remaining late total cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-
getBaseline1PlannedNonLaborCost
Gets the primary baseline planned nonlabor cost for this spread period.- Returns:
- the primary baseline planned nonlabor cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativeBaseline1PlannedNonLaborCost
Cost getCumulativeBaseline1PlannedNonLaborCost() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative primary baseline planned nonlabor cost for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated primary baseline planned nonlabor cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-
getActualCost
Gets the actual cost for this spread period.- Returns:
- the actual cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativeActualCost
Cost getCumulativeActualCost() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative actual cost for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated actual cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-
getBaselinePlannedMaterialCost
Gets the project baseline planned material cost for this spread period.- Returns:
- the project baseline planned material cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativeBaselinePlannedMaterialCost
Cost getCumulativeBaselinePlannedMaterialCost() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative project baseline planned material cost for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated project baseline planned material cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-
getBaseline1PlannedTotalCost
Gets the primary baseline planned total cost for this spread period.- Returns:
- the primary baseline planned total cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativeBaseline1PlannedTotalCost
Cost getCumulativeBaseline1PlannedTotalCost() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative primary baseline planned total cost for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated primary baseline planned total cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-
getBaseline1ActualLaborUnits
Gets the primary baseline actual labor units for this spread period.- Returns:
- the primary baseline actual labor units in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativeBaseline1ActualLaborUnits
Unit getCumulativeBaseline1ActualLaborUnits() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative primary baseline actual labor units for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated primary baseline actual labor units in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-
getBaseline1ActualNonLaborUnits
Gets the primary baseline actual nonlabor units for this spread period.- Returns:
- the primary baseline actual labor units in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativeBaseline1ActualNonLaborUnits
Unit getCumulativeBaseline1ActualNonLaborUnits() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative primary baseline actual nonlabor units for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated primary baseline actual nonlabor units in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-
getBaseline1ActualLaborCost
Gets the primary baseline actual labor cost for this spread period.- Returns:
- the primary baseline actual labor cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativeBaseline1ActualLaborCost
Cost getCumulativeBaseline1ActualLaborCost() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative primary baseline actual labor cost for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated primary baseline actual labor cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-
getBaseline1ActualNonLaborCost
Gets the primary baseline actual nonlabor cost for this spread period.- Returns:
- the primary baseline actual nonlabor cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativeBaseline1ActualNonLaborCost
Cost getCumulativeBaseline1ActualNonLaborCost() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative primary baseline actual nonlabor cost for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated primary baseline actual nonlabor cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-
getBaseline1ActualMaterialCost
Gets the primary baseline actual material cost for this spread period.- Returns:
- the primary baseline actual material cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativeBaseline1ActualMaterialCost
Cost getCumulativeBaseline1ActualMaterialCost() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative primary baseline actual material cost for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated primary baseline actual material cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-
getBaseline1ActualExpenseCost
Gets the primary baseline actual expense cost for this spread period.- Returns:
- the primary baseline actual expense cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativeBaseline1ActualExpenseCost
Cost getCumulativeBaseline1ActualExpenseCost() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative primary baseline actual expense cost for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated primary baseline actual expense cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-
getBaseline1ActualTotalCost
Gets the primary baseline actual total cost for this spread period.- Returns:
- the primary baseline actual total cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativeBaseline1ActualTotalCost
Cost getCumulativeBaseline1ActualTotalCost() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative primary baseline actual total cost for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated primary baseline actual total cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-
getPlannedLaborUnits
Gets the planned labor units for this spread period.- Returns:
- the planned labor units in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativePlannedLaborUnits
Unit getCumulativePlannedLaborUnits() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative planned labor units for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated planned labor units in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-
getAtCompletionLaborCost
Gets the at completion labor cost for this spread period.- Returns:
- the at completion labor cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativeAtCompletionLaborCost
Cost getCumulativeAtCompletionLaborCost() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative at completion labor cost for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated at completion labor cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-
getActualLaborUnits
Gets the actual labor units for this spread period.- Returns:
- the actual labor units in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativeActualLaborUnits
Unit getCumulativeActualLaborUnits() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative actual labor units for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated actual labor units in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-
getEarnedValueLaborUnits
Gets the earned value labor units for this spread period.- Returns:
- the earned value labor units in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativeEarnedValueLaborUnits
Unit getCumulativeEarnedValueLaborUnits() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative earned value labor units for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated earned value labor units in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-
getActualNonLaborCost
Gets the actual nonlabor cost for this spread period.- Returns:
- the actual nonlabor cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativeActualNonLaborCost
Cost getCumulativeActualNonLaborCost() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative actual nonlabor cost for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated actual nonlabor cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-
getBaseline1PlannedMaterialCost
Gets the primary baseline planned material cost for this spread period.- Returns:
- the primary baseline planned material cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativeBaseline1PlannedMaterialCost
Cost getCumulativeBaseline1PlannedMaterialCost() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative primary baseline planned material cost for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated primary baseline planned material cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-
getRemainingNonLaborUnits
Gets the remaining nonlabor units for this spread period.- Returns:
- the remaining nonlabor units in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativeRemainingNonLaborUnits
Unit getCumulativeRemainingNonLaborUnits() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative remaining nonlabor units for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated remaining nonlabor units in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-
getRemainingLateNonLaborUnits
Gets the remaining late nonlabor units for this spread period.- Returns:
- the remaining late nonlabor units in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativeRemainingLateNonLaborUnits
Unit getCumulativeRemainingLateNonLaborUnits() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative remaining late nonlabor units for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated remaining late nonlabor units in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-
getAtCompletionNonLaborUnits
Gets the at completion nonlabor units for this spread period.- Returns:
- the at completion nonlabor units in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativeAtCompletionNonLaborUnits
Unit getCumulativeAtCompletionNonLaborUnits() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative at completion nonlabor units for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated at completion nonlabor units in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-
getBaselinePlannedLaborUnits
Gets the project baseline planned labor units for this spread period.- Returns:
- the project baseline planned labor units in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativeBaselinePlannedLaborUnits
Unit getCumulativeBaselinePlannedLaborUnits() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative project baseline planned labor units for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated project baseline planned labor units in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-
getAtCompletionNonLaborCost
Gets the at completion nonlabor cost for this spread period.- Returns:
- the at completion nonlabor cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativeAtCompletionNonLaborCost
Cost getCumulativeAtCompletionNonLaborCost() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative at completion nonlabor cost for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated at completion nonlabor cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-
getPlannedLaborCost
Gets the planned labor cost for this spread period.- Returns:
- the planned labor cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativePlannedLaborCost
Cost getCumulativePlannedLaborCost() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative planned labor cost for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated planned labor cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-
getBaselinePlannedExpenseCost
Gets the project baseline planned expense cost for this spread period.- Returns:
- the project baseline planned expense cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativeBaselinePlannedExpenseCost
Cost getCumulativeBaselinePlannedExpenseCost() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative project baseline planned expense cost for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated project baseline planned expense cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-
getPlannedMaterialCost
Gets the planned material cost for this spread period.- Returns:
- the planned material cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativePlannedMaterialCost
Cost getCumulativePlannedMaterialCost() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative planned material cost for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated planned material cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-
getBaselineActualMaterialCost
Gets the project baseline actual material cost for this spread period.- Returns:
- the project baseline actual material cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativeBaselineActualMaterialCost
Cost getCumulativeBaselineActualMaterialCost() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative project baseline actual material cost for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated project baseline actual material cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-
getEstimateAtCompletionLaborUnits
Gets the estimate at completion labor units for this spread period.- Returns:
- the estimate at completion labor units in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativeEstimateAtCompletionLaborUnits
Unit getCumulativeEstimateAtCompletionLaborUnits() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative estimate at completion labor units for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated estimate at completion labor units in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-
getRemainingLaborCost
Gets the remaining labor cost for this spread period.- Returns:
- the remaining labor cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativeRemainingLaborCost
Cost getCumulativeRemainingLaborCost() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative remaining labor cost for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated remaining labor cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-
getRemainingLateLaborCost
Gets the remaining late labor cost for this spread period.- Returns:
- the remaining late labor cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativeRemainingLateLaborCost
Cost getCumulativeRemainingLateLaborCost() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative remaining late labor cost for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated remaining late labor cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-
getActualLaborCost
Gets the actual labor cost for this spread period.- Returns:
- the actual labor cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativeActualLaborCost
Cost getCumulativeActualLaborCost() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative actual labor cost for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated actual labor cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-
getBaselinePlannedNonLaborCost
Gets the project baseline planned nonlabor cost for this spread period.- Returns:
- the project baseline planned nonlabor cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativeBaselinePlannedNonLaborCost
Cost getCumulativeBaselinePlannedNonLaborCost() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative project baseline planned nonlabor cost for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated project baseline planned nonlabor cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-
getRemainingMaterialCost
Gets the remaining material cost for this spread period.- Returns:
- the remaining material cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativeRemainingMaterialCost
Cost getCumulativeRemainingMaterialCost() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative remaining material cost for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated remaining material cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-
getRemainingLateMaterialCost
Gets the remaining late material cost for this spread period.- Returns:
- the remaining late material cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativeRemainingLateMaterialCost
Cost getCumulativeRemainingLateMaterialCost() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative remaining late material cost for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated remaining late material cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-
getBaselineActualLaborUnits
Gets the project baseline actual labor units for this spread period.- Returns:
- the project baseline actual labor units in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativeBaselineActualLaborUnits
Unit getCumulativeBaselineActualLaborUnits() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative project baseline actual labor units for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated project baseline actual labor units in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-
getBaselineActualLaborCost
Gets the project baseline actual labor cost for this spread period.- Returns:
- the project baseline actual labor cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativeBaselineActualLaborCost
Cost getCumulativeBaselineActualLaborCost() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative project baseline actual labor cost for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated project baseline actual labor cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-
getPlannedValueLaborUnits
Gets the planned value labor units for this spread period.- Returns:
- the planned value labor units in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativePlannedValueLaborUnits
Unit getCumulativePlannedValueLaborUnits() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative planned value labor units for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated planned value labor units in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-
getBaselinePlannedNonLaborUnits
Gets the project baseline planned nonlabor units for this spread period.- Returns:
- the project baseline planned nonlabor units in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativeBaselinePlannedNonLaborUnits
Unit getCumulativeBaselinePlannedNonLaborUnits() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative project baseline planned nonlabor units for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated project baseline planned nonlabor units in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-
getEstimateToCompleteCost
Gets the estimate to completion for this spread period.- Returns:
- the estimate to complete
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativeEstimateToCompleteCost
Cost getCumulativeEstimateToCompleteCost() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative estimate to completion for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated estimate to complete
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-
getBaseline1PlannedExpenseCost
Gets the primary baseline planned expense cost for this spread period.- Returns:
- the primary baseline planned expense cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativeBaseline1PlannedExpenseCost
Cost getCumulativeBaseline1PlannedExpenseCost() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative primary baseline planned expense cost for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated primary baseline planned expense cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-
getBaselinePlannedTotalCost
Gets the project baseline planned total cost for this spread period.- Returns:
- the project baseline planned total cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativeBaselinePlannedTotalCost
Cost getCumulativeBaselinePlannedTotalCost() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative project baseline planned total cost for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated project baseline planned total cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-
getRemainingExpenseCost
Gets the remaining expense cost for this spread period.- Returns:
- the remaining expense cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativeRemainingExpenseCost
Cost getCumulativeRemainingExpenseCost() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative remaining expense cost for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated remaining expense cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-
getRemainingLateExpenseCost
Gets the remaining late expense cost for this spread period.- Returns:
- the remaining late expense cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativeRemainingLateExpenseCost
Cost getCumulativeRemainingLateExpenseCost() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative remaining late expense cost for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated remaining late expense cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-
getActualExpenseCost
Gets the actual expense cost for this spread period.- Returns:
- the actual expense cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativeActualExpenseCost
Cost getCumulativeActualExpenseCost() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative actual expense cost for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated actual expense cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-
getRemainingLaborUnits
Gets the remaining labor units for this spread period.- Returns:
- the remaining labor units in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativeRemainingLaborUnits
Unit getCumulativeRemainingLaborUnits() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative remaining labor units for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated remaining labor units in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-
getRemainingLateLaborUnits
Gets the remaining late labor units for this spread period.- Returns:
- the remaining late labor units in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativeRemainingLateLaborUnits
Unit getCumulativeRemainingLateLaborUnits() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative remaining late labor units for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated remaining late labor units in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-
getBaselineActualExpenseCost
Gets the project baseline actual expense cost for this spread period.- Returns:
- the project baseline actual expense cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativeBaselineActualExpenseCost
Cost getCumulativeBaselineActualExpenseCost() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative project baseline actual expense cost for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated project baseline actual expense cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-
getAtCompletionMaterialCost
Gets the at completion material cost for this spread period.- Returns:
- the at completion material cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativeAtCompletionMaterialCost
Cost getCumulativeAtCompletionMaterialCost() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative at completion material cost for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated at completion material cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-
getAtCompletionExpenseCost
Gets the at completion expense cost for this spread period.- Returns:
- the at completion expense cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativeAtCompletionExpenseCost
Cost getCumulativeAtCompletionExpenseCost() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative at completion expense cost for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated at completion expense cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-
getEarnedValueCost
Gets the earned value cost for this spread period.- Returns:
- the earned value cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativeEarnedValueCost
Cost getCumulativeEarnedValueCost() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative earned value cost for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated earned value cost in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-
getActualNonLaborUnits
Gets the actual nonlabor units for this spread period.- Returns:
- the actual nonlabor units in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loaded
-
getCumulativeActualNonLaborUnits
Unit getCumulativeActualNonLaborUnits() throws SpreadFieldNotFoundException, SpreadCumulativeDataNotLoadedExceptionGets the cumulative actual nonlabor units for this spread period, which is cumulated from the activity start to the end of this period.- Returns:
- the cumulated actual nonlabor units in hours
- Throws:
SpreadFieldNotFoundException- if this field was not loadedSpreadCumulativeDataNotLoadedException- if cumulative data was not loaded
-