Day 1 (4/01/2013)

Previous TopicNext TopicContents

On Day 1, three activities are marked complete, leaving only two activities remaining. The Data Date is then updated accordingly. At the time the ETL process is run, the actuals are captured from the schedule in the Burn Down.

Schedule Updates

Day 1 Schedule Updates graphic.

Burn Down Hours

Burn Down Hours Summary

At the time the ETL process is run on 4/01/2013 there are 20 hours remaining in the schedule. As all the activities still match the plan on 3/31/2013, there are 130 Total Hours, which is a combination of the Actual Units Burn and Remaining Units Burn.

This table shows a subset of the activity metrics that are summarized in the Burn Down Hours line-bar graph for Day 1.

Day 1 Burn Down Hours table.

Burn Down Counts

Burn Down Counts Summary

At the time the ETL process is run on 4/01/2013, there are two activities with hours remaining in the schedule. As all of the activities match the plan on 3/31/2013, there are seven Total Activities, which include activities with Remaining Units and all other activities included as of the sys_workdown_date ETL process snapshot.

This table shows a subset of the activity metrics that are summarized in the Burn Down Counts line-bar graph.

Day 1 Burn Down Counts table.



Legal Notices
Copyright © 1999, 2014, Oracle and/or its affiliates. All rights reserved.

Last Published Friday, January 31, 2014