This use case describes what happens when an activity starts on Day 2 and additional Remaining Units and Duration are added to the activity causing it to not finish as scheduled. In this use case, the activity finishes on the following day, 4/03/2013.
P6 Values Table
Field | Planned Value | Actual Value |
---|---|---|
Start | 4/02/2013 12:00 a.m. | 4/02/2013 12:00 a.m. |
Finish | 4/02/2013 10:00 a.m. | 4/03/2013 6:00 a.m. |
Duration | 10 hours | 30 hours |
Units | 10 | 30 (+20) |
Burn Down Results
Day | Remaining Units Burn | Actual Units Burn | Completed | Emergent Count |
---|---|---|---|---|
Day 0 (3/31) | 10 | 0 | 0 | 0 |
Day 1 (4/01) | 10 | 0 | 0 | 0 |
Day 2 (4/02) | 6 | 24 | 0 | 0 |
Day 3 (4/03) | 0 | 30 | 1 | 0 |
Legal Notices
Copyright © 1999, 2014,
Oracle and/or its affiliates. All rights reserved.
Last Published Friday, January 31, 2014