13 Summary Tab

The Summary Tab provides a project dashboard view of your study's progress. The Summary Tab contains four portlets: Project Health, Current Status, Summary Performance Trend, and Projected At Completion.

13.1 Arranging Summary View

The Summary Tab allows you to hide any portlets from your view. To hide a portlet, remove the check from the box next to the name of the portlet at the top of the page, or click the Close button on the portlet.

13.2 Detailed Summary View

For a detailed view of study performance, click the Detail link in the lower right-hand corner of the Project Health, Current Status, or Projected At Completion portlets. These links will take you to the control panel for the Tracking Detail Report.

13.3 Project Health Portlet

The Project Health Portlet provides the Schedule Performance (SP), Budget Performance (BP), and the Overall Performance (OP) for the labor fees and costs in your study. The cells containing these values are colored green, yellow, or red to indicate project health.

If you have any values that do not have a color, it means the study is exceeding expectations. If this is the case, your data should be reviewed to ensure there are no errors.

13.4 Current Status Portlet

The Current Status Portlet provides the fundamental earned value metrics for your project.

13.5 Study Performance Trend Portlet

The Study Performance Trend Portlet shows the Actual Payments (red), Earned Value (blue), and the Planned Value (green) across the entire timeline and costs of the study.

To see the value at any point on one of the lines, place your mouse pointer over the line. To zoom in to a section of the chart, click and drag your mouse over a desired section. To return to the all-study view, double click within the chart.

13.6 Projected at Completion Portlet

The Projected at Completion Portlet provides you with predictions of conditions in the project's future based on the current information available.


Note:

The estimated date calculation is capped at 4 times the study length. If the date exceeds this cap, N/A will be displayed.