Late Activities - Activities Scheduled to Finish Later Than the Project Baseline Section of the Schedule Check Report Dialog Box

Overview

Use this section to view activities that are scheduled to finish later than the project baseline. This indicates how well the project is performing against the currently selected baseline.

Only a subset of the activities in the open projects are checked. WBS summary activities, activities with an actual finish date, milestones, and Level of Effort activities are removed from the subset to create the list of activities checked for a Baseline Finish Variance of less than 0. The Actual percentage is calculated as the number of activities found that match the check divided by the total number of subset activities checked.

Screen Elements

Project ID field

The unique identifying code of the project containing the activity which failed the check.

Activity ID field

The unique identifying code of the activity which failed the check.

Activity Description field

The brief description of the listed activity.

Finish Variance (hours) field

The number of hours the task has been delayed.

Getting Here

  1. Click "" Projects.
  2. On the Projects navigation bar, click "" Activities.
  3. On the Activities page, click the Actions menu and select Run "" "" Check Schedule....
  4. In the Check Schedule dialog box:
    1. Select the Late Activities - Activities scheduled to finish later than the project baseline option.
    2. Click Check Schedule.
  5. In the Schedule Check Report dialog box, expand the Late Activities - Activities scheduled to finish later than the project baseline section.

Copyright information