Previous Topic

Next Topic

Book Contents

Working with Project Risks

The risk register on the Risks page is the main area of the application where you identify and manage risks for a project. Additionally, you can add risks to a project from the Projects EPS page, and add risks to a project and assign the risks to activities from the Activities page.

Once you add a risk to the risk register, you can perform further analysis on the risk and create one or more risk response plans which include activities to reduce the negative impact of the risk. See About Risk Response Plans.

Risks page illustrating the Activities detail window

Table of Project Risks Elements

Item

Description

item one

Risks toolbar. See Risks Toolbar.

item  two

Risks work area: Risks for all the projects you have open display in the risk register. You can group by field name, such as project name to view all risks organized by project, or create a filter to view only the risks that interest you.

When adding a risk to the risk register, you supply a name for the risk, identify the risk as a threat or an opportunity, identify the current status of the risk, identify the owner of the risk, and then assign the values for probability, schedule, cost, and any other applicable user-defined impacts. The values for probability, schedule, cost, and additional user-defined impacts are used to calculate the risk score.

Note: If the Probability, Cost, and Schedule fields are disabled, a risk scorning matrix has not been assigned to the project. You can still use the risk register to track your risks; however, you cannot use the qualitative risk analysis features in the application until you create a risk scoring matrix and assign it to the project.

item  three

Risks detail windows:

Response Plans: The area where you add response plans and response plan action items. See Working with Risk Response Plans.

Activities: The area where you associate scheduled activities in your project to an identified risk. Refer to the example above to see a list of the project activities impacted by risk R001: Concrete supply constrained.

Description: The area used to provide a detailed explanation of the risk.

Cause: The area used to explain why this risk is occurring.

Effect: The area used to describe the impact this risk has on this project.

Notes: The area used to capture any additional information regarding the risk.

Probability and Impact Diagram: The Probability and Impact Diagram (PID) is a graphical representation of the probability and impact thresholds assigned to the risk scoring matrix associated with the project.

Related Topics

Managing Project Risks


Copyright information