Schedule relationship lag calendar enumerations are used with schedule options to specify the
calendar used to calculate the lag between predecessors and successors for all activities.
Sets the flag that indicates how to auto-number activity IDs for new activities-Y/N - Y means
use the selected activity's activity ID as prefix, N means use standard auto-numbering based
on the prefix, suffix.
Sets the flag that indicates how to auto-number activity IDs for new activities-Y/N - Y means
use the selected activity's activity ID as prefix, N means use standard auto-numbering based
on the prefix, suffix.
Sets the total working time from the activity actual start date to the actual finish date (for
completed activities), or to the current data date (for in-progress activities).
Sets the value that determines whether the current or the new resource's Units per Time and
Overtime factor is used to calculate costs when assigning the resource to an existing activity
assignment.
Sets the option that determines whether the activity's actual and remaining units, start date,
finish date, and percent complete are computed automatically using the planned dates, planned
units and the schedule percent complete.
Sets the flag that identifies whether the actual and remaining costs for the expense are
computed automatically using the planned cost and the activity's schedule percent complete.
Sets the flag that identifies whether the activity actual and remaining units, start dates and
finish dates for the resource are computed automatically using the planned dates, planned
units and the activity's schedule percent complete.
Sets the flag that indicates whether batch creates and updates
should be aborted when the first exception occurs (the default
behavior), or whether the entire batch should be processed and then
all business rule exceptions reported in a single BatchException.
Sets the critical path type, which indicates how critical path activities are identified for
the project, based on either 'Critical Float' or 'Longest Path'.
Sets the critical path type, which indicates how critical path activities are identified for
the project, based on either 'Critical Float' or 'Longest Path'.
Sets the critical path type, which indicates how critical path activities are identified for
the project, based on either 'Critical Float' or 'Longest Path'.
Sets the default units/time setting, which determines the value of the remaining units/time
and planned units/time when a resource assignment is added.
Sets the date value that determines the early start date for imported activities with external
constraints lost (relations from/to external projects that do not exist in the database).
Sets the date value that determines the Late Finish Date for imported activities with external
constraints lost (from/to external projects that do not exist in the database).
Sets the Boolean value that determines whether a resource that is assigned to a project at
Project or WBS level, has that assignment for the duration of the project.
Sets the flag that indicates whether timesheet application users are allowed to log timesheet
hours on activities for dates after the activities' actual finish dates.
Sets the flag that indicates whether timesheet application users are allowed to log timesheet
hours on activities for dates prior to the activities' actual start dates.
Sets the flag that indicates whether timesheet application users are allowed to log timesheet
hours on activities that are already marked as completed.
Sets the flag that indicates whether timesheet application users are allowed to log timesheet
hours on activities that are still marked as Not started.
Sets the flag that indicates whether the responsible manager assigned to the Project
or WBS in Methodology Manager will be used, otherwise the responsible manager assigned
to the selected Project or WBS will be used.
Sets the value that determines which price/unit will be used by default to calculate costs for
the assignment when both a resource and role are assigned.
Sets the flag that indicates whether to reset Planned Duration and Units to Remaining Duration
and Units, or to reset Remaining Duration and Units to Planned Duration and Units when the
Activity Status is or becomes not started.
Sets the flag that indicates whether to reset Planned Duration and Units to Remaining Duration
and Units, or to reset Remaining Duration and Units to Planned Duration and Units when the
Activity Status is or becomes not started.
Sets the flag that indicates whether the project's resource can use the timesheet application
to update remaining units or percent complete for their activities.
Sets the flag that indicates whether the project's resource update the remaining units or the
percent complete for their activities in the timesheet application.
Sets the setting that indicates whether to recalculate the Duration, Units, or Units/Time for
existing assignments based on the activity Duration Type (true) or to preserve the Duration,
Units, or Units/Time for existing assignments (false) when adding or removing assignments on
activities.
Sets the flag that indicates whether the system uses the hours per time period defined in the
calendar.If this flag is true, the system uses the hours per time period settings that are
defined in the calendar.If this flag is false, the system uses the hours per time period from
the global preferences.
Sets the flag that indicates whether the price per unit will be copied from the methodology
and the rate source will be set to Override, otherwise the project rate type will be used
on all assignments
Summary spread interval enumerations are used with global preferences for specifying the interval
in which to summarize and store WBS, resource, and role level spreads.