Returns the number of Work-Days elapsed between the requested Dates. Example
if a calendar defines Monday through Friday as Workdays and a Holiday on 13-Sep-2006 then
calendarRule.elapsedDays('2006-09-11','2006-09-18')returns 4 working days
| Name | Type | Description | Mode |
|---|---|---|---|
| fromDate | Time | Begin Date | in |
| toDate | Time | End Date | in |